NORTHERN VALLEY 1 DER
The Northern Valley 1 DER Project is a natural gas-fired electric generation facility located approximately fourteen kilometres southeast of Elk Point, Alberta in the County of Two Hills.
The Project will have a nameplate capacity of 5 MW and is comprised of two 2.5 MW natural gas-fired high efficiency-low emissions industrial engines and electrical switchgear, located within modular buildings.
The Project connects to ATCO Electric's existing 25 kilovolt (kV) distribution line.
The necessary regulatory approvals are in place for the Project
with phase 1 construction commencing August 8, 2024.
Phase 2 construction is expected to commence in September 2024.
The Project will reach commercial operations in November 2024.